Clarington Indoor Soccer & Outdoor Lacrosse Facility
Clarington, Ontario

Construction completed April 2005
Mechanical and Electrical Design
Mechanical included:
· Water, Fire, Sanitary and Storm Services
· Building Heating and Ventilation for Indoor Soccer Facility
· HVAC Systems for Office, General Purpose and Changeroom Facilities
· Indoor Plumbing and Drainage for Washroom and Changeroom Facilities
· Fire Standpipe System
Electrical included:
· Incoming Primary
· Incoming Secondary
· Lacrosse Lighting
· Soccer Lighting
· Parking Lot Lighting
· Incoming Street Lighting
· Building Lighting
· Future Service to Other Facilities
Ballantrae Community Centre
Ballantrae, Ontario
Construction completed November 2004
Complete 30,000 sq. ft. high profile Community Centre for Ballantrae Golf Community
Mechanical included:
· Complete HVAC systems for game rooms, offices, meeting rooms and studios
· Hot water heating system for primary and secondary
· Kitchen ventilation and exhaust system
· Plumbing and drainage systems for washrooms, kitchen facility and general use
· Sprinkler system throughout
· Energy Management Control System
Electrical included:
· Site electrical power and lighting included photometrics review
· Main incoming power service including 400 Amp 600V service
· General and specialty lighting systems throughout including emergency and exit lighting
· Power and distribution systems for all building and computer system