Sprinklers and Fire Protection
_____________________________________
_____________________________________
Ryerson CCE
Toronto, Ontario

Construction completed Fall 2004
New 225,000 ft² Six Level Institutional Building
Complete Design of Sprinkler System
Hydraulic Calculations
Design included Fire Pumps and Window Sprinklers
ProFac - SNC Lavalin
2 Surrey Place, Toronto, Ontario

Construction completed 2004
Complete retrofit of existing fire alarm system to new addressable type for existing five story office building
Oshawa, Ontario

Construction completed 2003
Existing Warehouse and New Three Story Office Addition
Rework existing sprinkler service
Design of Sprinkler System for Existing Warehouse and Addition
Hydraulic Calculations
ABB / ACSYS New Paint Line
Oshawa, Ontario
Construction completed 2002
New Paint Line in Upgraded Area
Special Wet, Dry and Deluge Sprinkler Systems and Fire Alarm Systems
Clear Coat Robotic Paint Booth - Deluge System complete with IR³ detectors
Base Coat Robotic Paint Booth - Deluge System complete with IR³ detectors
Flash Tunnel
Heat Transfer Tunnel
Adpro Flash Tunnel
Filter Houses and ductwork
Cleanrooms
Abatement Duct
George Drew Complex
25 Grosvenor Street, Toronto, Ontario
Construction completed 2002
Existing 19 storey plus 2 basement levels and 2 mechanical penthouse levels, forensics office tower and 3 level pathology building
Commissioning of sprinkler system and life safety system upgrades and new installation
Sprinkler system included new sprinkler fire pumps and standpipe fire pumps
General Motors Experimental Building
Oshawa, Ontario
Construction completed 2001
New building - plant and two floor office area
Sprinkler drawings and hydraulic calculations for permit and construction
Coordinated with CIRI Insurance company for special requirements